In June 2024, the Tampa Bay Rays agreed to a $1.3 billion take care of each the town of St. Petersburg and Pinellas County. Publicly launched value estimates initially confirmed the town and county sharing $600 million, whereas the Rays would contribute $700 million. These numbers are insanely deceptive for a number of causes. First, they don’t embody the a whole bunch of thousands and thousands the town/county might want to spend on infrastructure enhancements. Two, these numbers don’t embody the dearth of property taxes. Third, there are nonetheless so many issues that we nonetheless don’t know concerning the settlement. Florida Tax Watch’s report calculates the mixed metropolis and county prices at roughly $2.4 billion.
In July 2024, the events concerned within the negotiations reached an settlement to construct a brand new ballpark. However finishing this settlement required approval from each the town council and county commissioners, a course of anticipated to final months. Town council signed off on the deal, however in late October, Pinellas Commissioners needed to delay their vote on account of two hurricanes hitting the world. Due to these delays, two newly elected commissioners would now vote on this deal, relatively than the earlier commissioners. These two had some points with this deal, and the county pushed again the vote to December. On the December assembly, the county handed the settlement because of the MLB commissioner speaking to the 2 new commissioners.
Nevertheless, the Rays didn’t attend the vote and had different plans:
“As we’ve made clear, the County’s delay has precipitated the ballpark’s completion to slip into 2029. Because of this, the price of the undertaking has elevated considerably, and we can’t soak up this improve alone. When the County and Metropolis want to interact, we stay prepared to unravel this funding hole collectively.” – Rays president Matt Silverman, Tampa Bay Times, 12/17/24
Everybody thought the deal was again on. Although the county had pushed again the vote a number of instances, there have been no missed deadlines. IMPORTANT TO REMEMBER: THE AGREEMENT DOES NOT GIVE DATE DEADLINES FOR THE CITY/COUNTY TO APPROVE THE DEAL.

One member of the Pinellas County Fee despatched a letter to the crew asking for a response from them on whether or not the Rays intend to “commit to a new $1.3 billion ballpark, or if they’re walking away from the deal”. The crew wrote again and declared that the present ballpark settlement was in impact “until a party terminates”. The crew additionally claimed that they’d “fulfilled its obligations to date and continue to wait on the city and county”. Wait, so the Rays simply mentioned that the settlement is at the moment in impact? Then why do they preserve operating to the native media and demanding further cash from the town/county?
Primarily, the Rays in writing argue that the deal is at the moment shifting ahead till somebody formally backs out. However throughout interviews with the native media, the crew clarifies they want extra taxpayer cash to ensure that the deal to proceed as a result of the vote in December precipitated “significantly increased construction costs”. The issue with this argument is that the Rays proceed to both disguise or lie about these elevated prices. No one has seen any proof or proof of this improve. One commissioner, who supported the Rays deal, known as the crew’s feedback “laughable”. The Tampa Bay Instances has reported that different metropolis leaders blame the Rays for this public confrontation and “expressed skepticism that construction prices have risen so much in so short a time”. When one commissioner requested a advisor who had labored on 25 stadium offers whether or not he had ever seen a crew lose $200M due to a 30-day delay, the advisor “said he had never seen that”.

Fortunately, some metropolis leaders are placing their foot down with the Rays and telling them to make the subsequent transfer. One metropolis commissioner talked about to the Tampa Bay Instances that “The onus is on them” and one other famous that everybody is now trying to see if the “Rays uphold their part of this deal”. Presently, the Rays contractually have the subsequent obligation to fulfill. By March 31, the crew should show that they’ve accomplished a number of obligations if they need extra public cash to be unlocked and given to them. If the Rays don’t fulfill their obligation by March 31, then the “deal automatically terminates”. Backing out would trigger the Rays to be “in default” and due to this fact lose “their development rights for the district”. The crew responded by asserting that they have been “meeting four out of 13 conditions”.
My favourite half about this response was that the crew “did not send any documentation as proof”. Nevertheless, the crew did state that they “had spent $11.6 million” already. Maintain on. Didn’t the crew ship a letter in November to county commissioners claiming that the crew had spent $50M on the undertaking? I’m wondering why the Rays are giving completely different numbers to completely different individuals. Weeks have passed by, and everybody waits for the Rays to say one thing or produce some proof of this elevated value. Nothing.
Nevertheless, I noticed an article at this time within the Tampa Bay Instances, the place the Rays proprietor admits that “they are still deciding what to do”. When requested how a lot cash he’s asking from the town/county, he “wouldn’t say how much more money the Rays need” to compensate them for the delayed vote.

However what blew my thoughts was what the mayor of Tampa Bay advised the media:
Welch met with Sternberg final week and has one other assembly with him Tuesday to ask if Sternberg has made any progress in his considering on the deal and if the crew is ready to fulfill its obligations…Welch mentioned they’ve talked concerning the Rays’ place of getting elevated prices due to the county’s delayed votes, however mentioned he nonetheless hasn’t seen something that itemizes or reveals what that value is when it comes to {dollars}. “I don’t know if that’s nonetheless a problem for them or not, however we have to get some certainty” Welch mentioned, including that he desires to be “clear and clear” about what the potential path ahead — Tampa Bay Times, 01/27/25
Wait, what? The crew has not even given the mayor a single factor that confirmed what they’ve been crying about for a month? Will they ever? Let’s preserve this easy and have a look at the contract between the town/county and the crew. Who particularly is on the hook for value overruns? Wouldn’t this simply be an elevated value? In line with the contract settlement: “Rays are on the hook for all cost overruns”.

For the reason that Rays proprietor isn’t even placing in more than $150M of his personal cash, why not have a look at him to pay?